You need additional tools and equipment to complete the installation tasks.
Item | Included with the cabinet | |
---|---|---|
3/4-in. wrench (supplied in the shipping crate) – To raise and lower the leveling feet under the cabinet. 1/4-in. Allen wrench – To raise and lower the stability foot in the front of the cabinet. |
||
NEMA L6-30 |
AC power cords
– To connect the cabinet to external power sources (wall plugs).
Note: Each PDU must be connected to an independent power source.
|
|
IEC-60309 |
||
SAS cables (optional) – Two cables are included with each drive tray, while host side cables must be purchased separately. Communication cables (optional) – To attach the tray to the host. Refer to the appropriate controller-drive tray installation guide for additional required items. |
||
Mountable cable spools – Installed along both sides of the vertical power distribution outlets to accommodate excess cable length and cable routing. Two cable spools are included with each controller-drive tray. Cable spools are also shipped with standalone drive trays. |
||
Shears – To cut the metal bands on the shipping crate. |
||
Forklift (optional) – To remove the cabinet from the shipping pallet. |
||
Front panel kits (optional) – To cover the empty bays at the front of the cabinet. |
||
Antistatic bags (optional) – To protect components that are removed during the installation procedure for the cabinet. |