Table of ContentsView in Frames

Monitoring the volume move status

You can use the vol move status command to display information about the volume that is moved.

About this task

Note: If you are running the vol move status command in a continuous loop during cutover phase, you might see a message indicating that vol move is complete even before actual completion. This may not be indicating actual cutover completion. To confirm, wait a few sections and run vol move status again.

Step

  1. Obtain the status of the volume move operation by entering the following command:
    vol move status srcvol [-v]

    -v provides additional information about the destination volume name, amount of data transferred, the time taken for the data transfer, and the amount of data that is currently being transferred.

Example

system1> vol move status vol1 -v
Source				: vol1
Destination			: aggr1:ndm_dstvol_1188375081
State					: move
Cutover Attempts	: 3
Cutover Time		: 60
Last Completed Transfer:
        Data Transferred = 324 KB       Time Taken = 1 s
Current Transfer Size = 0 KB