Cabling the controller
You must cable the Fibre Channel ports on the controller to the Brocade or Cisco switches.

-
Determine which Fibre Channel ports on your system that you want to use and create a list showing the order you want to use them.
Note: The numbers in the example refer to the preferred order of usage, not the port ID. For example, Fibre Channel port 1 might be port 0a on the controller.
- Cable the first two Fibre Channel ports of Node A to the same numbered ports on Switch 1 and Switch 2, for example, port 1.
-
Cable the second two Fibre Channel ports of Node A to the same numbered ports on Switch 1 and Switch 2, for example, port 2.
Note: The switches in the example are 16-port switches.