Table of ContentsView in Frames

Cabling the ISLs between MetroCluster sites

You must connect the FC switches at each site through the fiber-optic Inter-Switch Links (ISLs) to form the switch fabrics that connect the MetroCluster components.

About this task

This task includes steps performed at each MetroCluster site.

Up to four ISLs per FC switch fabric are supported.

Step

  1. Connect the FC switches at each site to the ISL or ISLs.
    This must be done for both switch fabrics.
    Note: The Brocade and Cisco switches use different port numbering:
    • On Brocade switches, the first port is numbered 0.
    • On Cisco switches, the first port is numbered 1.
    The port numbering is shown in the following table:
    ISL Site A Site B
    To this port on FC_switch_A_x... To this port on FC_switch_B_x...
    Brocade 6505 Brocade 6510 Cisco 9148 Brocade 6505 Brocade 6510 Cisco 9148
    First ISL 8 20 36 8 20 36
    Second ISL 9 21 40 9 21 40
    Third ISL 10 22 44 10 22 44
    Four ISL 11 23 48 11 23 48